A bank branch office plans to do an office space expansion project and all the activities of this project are provided in the following table.
A bank branch office plans to do an office space expansion project and all the activities of this project are provided in the following table.
Activity
Immediate Predecessors
Duration Weeks
Available Weeks to crash
Crash cost per week
A
NA
B
$
C
B
$
D
AB
$
E
C
$
F
C
$
G
DF
$
H
EG
$
If the indirect costs for the project total $ per week, how many weeks would you recommend to the bank that the project be shortened in order to minimize the total cost including direct cost and indirect cost
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started