Question

1 Approved Answer

A certain project is being negotiated between a buyer and a seller. The project is a research project that has unknown deliverables. The buyer and

A certain project is being negotiated between a buyer and a seller. The project is a research project that has unknown deliverables. The buyer and seller are discussing the type of contract that should be agreed (fixed price or cost reimbursable). The buyer wants the seller to engage in a fixed price contract. What should the seller do? Why? Using the "Project Procurement Template,"provide the following, as instructed.

A certain project operating under a CPIF contract has been negotiated and formally agreed-upon between a buyer and a seller. The following information has been included in the contract:

  • Target Price: $223,096
  • Target Cost: $215,000
  • Target Fee: $8,000
  • Buyer's Share Ratio: 0.70
  • Seller's Share Ratio: 0.30

The project has finished and the actual cost that the seller incurred was $207,643.

  1. What incentive fee does the buyer pay the seller?
  2. What is the total contract price (i.e., what the buyer has to pay the seller in total)?

A certain project operating under a FPIF contract has been negotiated and formally agreed-upon between a buyer and a seller. The following information has been included in the contract:

  • Price Ceiling: $531,000
  • Target Cost: $505,000
  • Target Fee: $20,000
  • Buyer's Share Ratio: 0.90
  • Seller's Share Ratio: 0.10

The project has finished and the actual cost the seller incurred was $510,954.

  1. What incentive fee does the buyer pay the seller?
  2. What is the total contract price (i.e., what the buyer has to pay the seller in total)?
  3. What is the point of total assumption for the seller?

Submit the completed file, "Project Procurement Template" (i.e. MS Excel file), ensuring your last name is included in the

image text in transcribed
> Part 2 Target Price: Target Cost: Target Fee: 10 Buyer's Share Ratio: Seller's Share Ratio: Actual Cost Contract Price: 15 Incentive Fees: 16 18 19 Part 3 20 Price Ceiling: Target Cost: Target Fee: 23 Buyer's Share Ratio: Seller's Share Ratio: Actual Cost: Contract Price: 28 Incentive Fees 29 Assumption Point: 30 32 33 Sheet1 + 100% Ready Accessibility: Good to go

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions