Question

1 Approved Answer

A firm with a 1 3 % WACC is evaluating two projects for this year's capital budget. After - tax cash flows, including depreciation, are

A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:
012345
Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000
Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400
Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations.
Project M $
Project N $
Calculate IRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M %
Project N %
Calculate MIRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M %
Project N %
Calculate payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M years
Project N years
Calculate discounted payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M years
Project N years
Assuming the projects are independent, which one(s) would you recommend?
If the projects are mutually exclusive, which would you recommend?
Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR?A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:
a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations.
Project M :
Project N$
Calculate IRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Calculate MIRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M
%
Project N
%
Calculate payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M years
Project N years
Calculate discounted payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M
years
Project N
years
b. Assuming the projects are independent, which one(s) would you recommend?
-Select-
c. If the projects are mutually exclusive, which would you recommend?
-Select-
d. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR?
-Select-
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Health Care Finance Basic Tools For Nonfinancial Managers

Authors: Judith J. Baker, R.W. Baker, Neil R. Dworkin

5th Edition

1284118215, 978-1284118216

More Books

Students also viewed these Finance questions