A manager wants to assign tasks to workstations as efficiently as possible. The immediate predecessors and task times are provided in the dataset under provided

  1. A manager wants to assign tasks to workstations as efficiently as possible. The immediate predecessors and task times are provided in the dataset under provided table. 
  2. (5 points) Draw the precedence diagram.
  3. (5 points) Assuming a 7.5-hour workday, compute the cycle time needed to obtain an output of 225 units per day.
  4. (5 points) Determine the minimum number of workstations required.
  5. (5 points) Assign tasks according to greatest positional weight (sum of each task's time and the times of all following tasks)
  6. (5 points) Compute the resulting percent idle time for each worker (workstations). 
TaskImmediate PredecessorTask time in min
a-----0.2
ba0.8
cb0.4
d-----0.7
ed0.6
f-----0.7
gf0.8
hg0.6
ic, e, h0.5
ji0.1
kj0.2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Lets go through each step to solve this problem Precedence Diagram The precedence diagram shows the sequence of tasks and their dependencies Task a 02 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
66428e5e316a6_979174.pdf

180 KBs PDF File

Word file Icon
66428e5e316a6_979174.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson, Mehran Hojati

4th Canadian edition

978-1259270154, 1259270157, 978-0071091428

More Books

Students also viewed these Business Communication questions