A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at
A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take? A. Continue to monitor the system performance. B. Resize the resource utilization to reflect current needs. C. Reinforce adoption over time. D. Raise an item in the issue log