A product has to be processed in milling and turning. The lot size is 100 , the milling time per piece 1 turning time per
A product has to be processed in milling and turning. The lot size is 100 , the milling time per piece 1 turning time per piece 1.1 minutes. The setup time of the milling machine is 24 minutes, the setup time machine is 10 minutes. Which machine is the bottleneck machine? A. The milling machine B. The turning machine