Question: A sewer pipe is to be laid from station 1 0 + 0 0 to station 1 2 + 5 0 on a + 0

A sewer pipe is to be laid from station 10+00 to station 12+50 on a +0.25% grade, starting with invert elevation 845.22ft at 10+00, Calculate invert elevations at each 50-ft station along the line.