An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job | Description | Predecessor | Expected time in days |
A | Prepare preliminary sketches | NA | 2 |
B | Outline specifications | NA | 1 |
C | Prepare drawings | A | 3 |
D | Write specifications | A B | 2 |
E | Run prints | C D | 1 |
F | Have specifications printed | B D | 3 |
G | Assemble bid package | E F | 1 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started