An equipment installation job in the completion stage can be completed in 40 days of 8 hour day work with 40 men working. With the
An equipment installation job in the completion stage can be completed in 40 days of 8 hour day work with 40 men working. With the contract expiring in 30 days, the civil engineer contractor decided to add 10 men on the job, overtime not being permitted. If the liquidated damages is P2,500 per day of delay and the men are paid P270 per day, will the engineer be able to complete the job on time? How much would he save with the addition of workers?