An IT software project comprises the following activities, whose time estimates are given against each other as below: Activity Estimated Duration (weeks) - Optimistic Most
An IT software project comprises the following activities, whose time estimates are given against each other as below:
Activity | Estimated Duration (weeks) | ||
- | Optimistic | Most Likely | Pessimistic |
1-2 | 3 | 6 | 15 |
1-3 | 2 | 5 | 14 |
1-4 | 6 | 12 | 30 |
2-5 | 2 | 5 | 8 |
2-6 | 5 | 11 | 17 |
3-6 | 3 | 6 | 15 |
4-7 | 3 | 9 | 27 |
5-7 | 1 | 4 | 7 |
6-7 | 4 | 19 | 28 |
a) Find the critical path for the project. (10 marks)
b) Whatis the expected project duration? (10 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started