An IT software project comprises the following activities, whose time estimates are given against each other as below: Activity Estimated Duration (weeks) - Optimistic Most

An IT software project comprises the following activities, whose time estimates are given against each other as below:

Activity Estimated Duration (weeks)
- Optimistic Most Likely Pessimistic
1-2 3 6 15
1-3 2 5 14
1-4 6 12 30
2-5 2 5 8
2-6 5 11 17
3-6 3 6 15
4-7 3 9 27
5-7 1 4 7
6-7 4 19 28

a) Find the critical path for the project. (10 marks)

b) Whatis the expected project duration? (10 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements , Rose Baker

7th Edition

1337095478, 978-1337095471

More Books

Students also viewed these General Management questions

Question

When would you use a surrogate key?

Answered: 1 week ago

Question

=+vii. Bullet points to emphasize important ideas.

Answered: 1 week ago