Question
Apply the critical chain process assuming that testing is a bottleneck resource (and that the other resources required are not constrained).Use due date as a
Apply the critical chain process assuming that testing is a bottleneck resource (and that the other resources required are not constrained).Use due date as a basis for priority.Apply the critical chain process to schedule, identifying buffers by type:
Use resource buffers before bottleneck resource
Use feeder buffers before interfaces between slack activities and critical activities
Use project buffer
Assumptions:
analysis must be done prior to production
production completed prior to testing
testing done prior to installation.
the schedule:
JobAnalysisProductionTesting InstallationDue date
A14 weeks4 weeks4 weeks2 weeksWeek 15
A24 weeks4 weeks4 weeks2 weeksWeek 10
A34 weeks8 weeks4 weeks2 weeksWeek 20
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started