Audio Products, Inc. produces two AM/FM/CD players for cars. The radio/CD units are identical, but the mounting hardware and finish trim differ. The standard model

Audio Products, Inc. produces two AM/FM/CD players for cars. The radio/CD units are identical, but the mounting hardware and finish trim differ. The standard model fits intermediate and full-sized cars, and the sports model fits small sports cars. Audio Products handles the production in the following way. The chassis (radio/CD unit) is assembled in Mexico and has a manufacturing lead time of two weeks. The mounting hardware is purchased from a sheet steel company and has a three-week lead time. The finish trim is purchased from a Taiwan electronics company with offices in Los Angeles as prepackaged units consisting of knobs and various trim pieces. Trim packages have a two-week lead time. Final assembly time may be disregarded because adding the trim package and mounting are performed by the customer. Audio Products supplies wholesalers and retailers, who place specific orders for both models up to eight weeks in advance. These orders, together with enough additional units to satisfy the small number of individual sales, are summarized in the following demand schedule:

WEEK

Model 1 2 3 4 5 6 7 8
Standard model 305 420
Sports model 218 120

There are currently 55 radio/CD units on hand but no trim packages or mounting hardware. Prepare a material requirements plan to meet the demand schedule exactly. Specify the gross and net requirements, on-hand amounts, and the planned order release and receipt periods for the radio/CD chassis, the standard trim and sports car model trim, and the standard mounting hardware and the sports car mounting hardware. (Leave the cells blank, whenever zero (0) is required.)

Period: 1 2 3 4 5 6 7 8
Standard Model Demand: 305 420
Sports Model Demand: 218 120
Radio/CD OH: 55 LT: 2 SS: 0 Q: L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Standard Trim OH: 0 LT: 2 SS: 0 Q: L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Standard HW OH: 0 LT: 3 SS: 0 Q: L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Sport Trim OH: 0 LT: 2 SS: 0 Q: L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Sport HW OH: 0 LT: 3 SS: 0 Q: L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forensic Accounting And Fraud Investigation For Non-Experts

Authors: Stephen Pedneault, Frank Rudewicz, Howard Silverstone, Michael Sheetz

3rd Edition

0470879599, 9780470879597

More Books

Students also viewed these Accounting questions