Bloom and Co. has no debt or preferred stock it is an all-equity firm and has a beta of 2.0. The CFO is evaluating a

  1. Bloom and Co. has no debt or preferred stock it is an all-equity firm and has a beta of 2.0. The CFO is evaluating a project with an expected return of 14%, before any risk adjustment. The current WACC of the company is 13%. The project being evaluated is riskier than an average project, in terms of both its beta risk and its total risk. Which of the following statements is correct? Why?

  1. The project should definitely be accepted because its expected return (before any risk adjustments) is greater than its required return.
  2. Riskier-than-average projects should have their expected returns increased to reflect their higher risk. Clearly, this would make the project acceptable regardless of the amount of the adjustment.
  3. The accept/reject decision depends on the firm's risk-adjustment policy. If Weatherall's policy is to increase the required return on a riskier-than-average project to 3% over rS, then it should reject the project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Art Of Tehnical Analysis

Authors: Strahinja Osmokrovic

1st Edition

979-8852314680

More Books

Students also viewed these Finance questions

Question

Plot the points (-5, 3) and (-2, -4) in coordinate system.

Answered: 1 week ago