cenario 1 2 . 1 3 Demand = 1 0 0 , 0 0 0 units / year Number of days per year = 2

cenario 12.13
Demand =100,000 units/year
Number of days per year =250 weeks
Standard deviation of weekly demand =50 units
Average lead time =5 days
Standard deviation of lead time: 2 days
Cycle-service level =99%
A continuous review system is used to control inventory.
A normal distribution table follows.
Use the information in Scenario 12.13. If the firm decides to reduce its cycle-service level to 95%, what is the new reorder point if all other parameters remain the same for this product?
Greater than 4,500 units
Greater than 3,500 units but less than or equal to 4,500 units
Greater than 2,500 units but less than or equal to 3,500 units
Greater than 1,500 units but less than or equal to 2,500 units
Greater than 0 but less than or equal to 1,500 units

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions

Question

understand possible effects of ethnicity;

Answered: 1 week ago