Question

1 Approved Answer

Complete the MRP schedule for the product below. Product A Lot Size = 200 Safety Stock = 50 Lead Time = 2 weeks Allocated =

  1. Complete the MRP schedule for the product below.

Product A Lot Size = 200

 Safety Stock = 50

 Lead Time = 2 weeks Allocated = 100 In hand =500

 WEEKS 

 1

 2

 3

 4

 5 

Gross requirement

300

500

800

400

Scheduled receipt

100

Available

Net requirements

Planned order receipts

Planned order releases

  1. Product X has the structure given below. 



P2 R3 S4

 Q4 T3 V2

  •  If 50 units of product X has to be produced, compute the bill of materials.

ITEM

QUANTITY

P

R

S

Q

T

V

  • Given the following lead times draw the time phased product structure for X

if delivery is desired in week 10 from now. 

ITEM

LEAD TIME

 IN WEEKS

X

1

P

2

Q

1

R

3

S

2

T

1

V

2



 1 2 3 4 5 6 7 8 9 10 

Step by Step Solution

3.37 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

Given the formula in the notes the MRP schedule is as below Lot Siz... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

3rd edition

132747324, 978-0132747325

More Books

Students also viewed these Economics questions

Question

Find the lengths of the curves. x = (y 3 /12) + (1/y), 1 y 2

Answered: 1 week ago