Question

1 Approved Answer

Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building that is expected to be completed in September 2023, at an

Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building that is expected to be completed in September 2023, at an estimated cost of $22,000,000. At the end of 2021, the costs to date were $10,120,000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $4,800,000 and the cash collected during 2021 was 3,200,000. Cooper uses the percentage-of-completion method.

For the year ended December 31, 2021, Cooper would recognize gross profit on the building of:

$ 843,333

$ 920,000

$1,080,000

$0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Frauds Of The Past Lessons For The Future A Student Led Journey Through The World Of Auditing

Authors: Dr. Manjari Sharma, Mr. Pragadeesh SP, Mr. Sivanaresh A

1st Edition

B0CGKRP289, 978-6206753247

More Books

Students also viewed these Accounting questions