Coronado Company prepared the following data in its static budget based on 140000 machine hours: Direct Materials $ 446000 Direct Labour 224000 Variable Overhead 1129000
Coronado Company prepared the following data in its static budget based on 140000 machine hours:
Direct Materials | $ 446000 |
Direct Labour | 224000 |
Variable Overhead | 1129000 |
Fixed Overhead | 2103000 |
Actual Results: | |
Machine Hours | 150000 hours |
Direct Materials | $470000 |
Direct Labour | 241000 |
Variable Overhead | 1154000 |
Fixed Overhead | 2106000 |
What is the budgeted Direct Labour cost at the actual level of activity?
A. $241000
B. $240000
C. $209067
D. $17000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started