ctivity Immediate Predecessor ( s ) Time ( days ) A - 5 B A 2 C A 4 D B 5 E B 5

ctivity Immediate Predecessor(s) Time (days)
A -5
B A 2
C A 4
D B 5
E B 5
F C 5
G E, F 2
H D 3
I G, H 5