Days Required Process customer order 0.2 Wait for direct materials to arrive 2.0 Fabrication of parts 4.0 Move order to assembly department 0.8 Wait for

Days Required
Process customer order 0.2
Wait for direct materials to arrive 2.0
Fabrication of parts 4.0
Move order to assembly department 0.8
Wait for machine time 7.0
Assembly of parts 2.0
Move order to finishing department 0.5
Wait for machine time 2.0
Finishing of units 4.0
Move to packing department 0.5
Packing 1.6
Move to shipping department 0.2
Load delivery truck 0.6
Drive to customer 1.5
Unload delivery truck 0.9
Return to plant

1.0

i need two things

Delivery cycle time

was 25.4

what is Manufacturing cycle time ? and Value-added time ?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

Describe the key elements of a just-in-time costing system.

Answered: 1 week ago