Question

1 Approved Answer

Description This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for

Description
This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the project below.
Instructions
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 21 days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than the agreed 21 days.
Draw a project network given the information below. Then, do the following:
Complete the forward and backward pass
Determine the critical path
Compute the Total slack for all activities
Determine which activities have free float
\table[[ID,Activity,Predecessor,Duration],[A,Prepare Site,None,2],[B,Pour Foundation,A,3],[C,Erect Frame,B,4],[D,Roof,C,4],[E,Windows,C,1],[F,Doors,C,1],[G,Electrical,C,3],[H,Rough-In Frame,D,E,F,2],[I,Door Opener,F, G,1],[J,Paint,H, I,2],[K,Clean Up,J,1]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Research Applications And Algorithms

Authors: Wayne L. Winston

4th Edition

0534380581, 9780534380588

More Books

Students also viewed these General Management questions