Determine question 3 3 to 3 6 based on the following problem ( Table 1 - 2 ) : Table 1 - 2 Immediate Most

Determine question 33 to 36 based on the following problem (Table 1-2):
Table 1-2
Immediate
Most
Activity Predecessor Optimistic Likely Pessimistic
A
4
5
6
B
12
16
18
C
A
2
8,14
D
A
5
5
5
E
B, C
6
7
8
According to Table 1-2, there are five activities in a PERT project. Which activities are on the critical path?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of strategic management

Authors: Charles w. l. hill, Gareth r. Jones

3rd Edition

1111525196, 978-1111525194

More Books

Students also viewed these General Management questions