Question
1 Approved Answer
d. Draw the resource loading profile for Carpenters given the following requirements: One carpenter is needed for activities A B, C, D, and E. Two
d. Draw the resource loading profile for Carpenters given the following requirements: One carpenter is needed for activities A B, C, D, and E. Two carpenters are needed for activity F.
e. What is the peak number of Carpenters needed?
f. What is the utilization of Carpenters?
g. Level within slack to reduce the peak number of Carpenters to 2. Redraw the Gantt chart and the resource loading profile.
h. What is the revised utilization? Network for problem 14.
a. Critical path is the list of activities that are marked in 'red circles". Start 0 71 0 0 0 4 4 0 0 1 1 A 1 1C C 1 B 1C 2 1C 3 Critical path C-E-F = 3+ 4+2 = 9 weeks 3 3 5 2 3 2 3 5 3 0 3 D NO 1C 2 m 1C 4 4 7 7 7 7 0 7 4. 2C 2 9 9
Step by Step Solution
★★★★★
3.40 Rating (153 Votes )
There are 3 Steps involved in it
Step: 1
DIRE D OO are four and slack listed in table in part ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started