Drexel Co. has a price variance of $5,000 (U) and a quantity variance of $4,000 (F) for raw materials. Given that the actual costs for
Drexel Co. has a price variance of $5,000 (U) and a quantity variance of $4,000 (F) for raw materials. Given that the actual costs for raw material are $40,000, what are the standard costs of raw materials?