During 2014, Nilsen Company started a construction job with a contract price of $1,610,000. The job was completed in 2016. The following information is available.

During 2014, Nilsen Company started a construction job with a contract price of $1,610,000. The job was completed in 2016. The following information is available.

2014 2015 2016
Costs incurred to date $393,190 $832,960 $1,112,000
Estimated costs to complete $565,810 $263,040 0
Billings to date $301,300 $900,200 $1,610,000
Collections to date $263,700 $801,300 $1,376,000

image text in transcribed

Show work

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2014 Gross profit recognized in 2015 Gross profit recognized in 2016 247,380 390,640 498,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Special Edition Of Managerial Accounting Volume 2 For Miami Dade College

Authors: WilD

4th Edition

0077542711, 978-0077542719

More Books

Students also viewed these Accounting questions

Question

1. Identify three approaches to culture.

Answered: 1 week ago

Question

2. Define communication.

Answered: 1 week ago

Question

4. Describe how cultural values influence communication.

Answered: 1 week ago