Question
During July, the following costs were incurred: Materials (30,000 units) $24,900 Labour and overheads $20,075 At the beginning of July, there were 15,000 units of
During July, the following costs were incurred:
Materials (30,000 units) $24,900
Labour and overheads $20,075
At the beginning of July, there were 15,000 units of work in progress valued as follows:
Materials (100% complete) $9,000
Labour and overheads (40% complete) $1,250
At the end of July, there were 5,000 units of work-in-progress. They were 100% complete for materials and 50% complete for labour and overheads.
Using both FIFO approach and Weighted Average approach:
(a) calculate how many units were completed during July
(b) calculate the cost per unit
(c) value the finished items and the closing work-in-progress
(d) create a Process Account. (Note: assume no losses)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started