Question
1 Approved Answer
During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure
During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and
infrastructure dependencies to deliver the expected value.
How should the project manager handle this issue?
Support the project team so technical debt and infrastructure dependencies are included in the next sprint.
Support the project sponsor so the decision is made topdown and the team follows the provided direction.
Support the product owner so only items with high business value are included in the next sprint.
Support a voting exercise so all team members can express their opinion and the reason behind their vote.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started