Question
Each of 8 jobs needs to go through work center A and B. Find the optimal sequence of jobs to minimize the makespan using Johnson's
- Each of 8 jobs needs to go through work center A and B. Find the optimal sequence of jobs to minimize the makespan using Johnson's rule.
Processing Time in hours | ||||
Job | Work center A | Work center B | ||
A | 4.0 | 2.4 | ||
B | 7.4 | 5.9 | ||
C | 8.5 | 9.4 | ||
D | 1.7 | 3.0 | ||
E | 4.4 | 5.4 | ||
F | 2.5 | 6.6 | ||
G | 6.7 | 5.1 | ||
H | 5.6 | 0.9 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Operations management
Authors: Jay Heizer, Barry Render
10th edition
978-0136119418, 136119417, 978-0132163927
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App