Question

1 Approved Answer

Example: Determining Standard Time Given: The normal time to perform the regular work cycle is 3 . 2 3 min. In addition, an irregular work

Example: Determining Standard Time
Given: The normal time to perform the regular work cycle is 3.23min. In addition, an irregular work element with a normal time =1.25 min is performed every 5 cycles. The PFD allowance factor is 15%.
Determine (a) the standard time and (b) the number of work units prodced during an 8-hr shift if the worker's pace is consistent with standard performance.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of strategic management

Authors: Charles w. l. hill, Gareth r. Jones

3rd Edition

1111525196, 978-1111525194

More Books

Students also viewed these General Management questions

Question

Analyse the process of new product of development.

Answered: 1 week ago

Question

Define Trade Mark.

Answered: 1 week ago