Fence 2 The Fence You have a project to build a new fence. The fence will form a square, as shown at right. Each side

image text in transcribed
Fence 2 The Fence You have a project to build a new fence. The fence will form a square, as shown at right. Each side is to take one day to build, and $1,500 has been budgeted per side. The sides were planned to be completed one after the other; however, circumstances changed on the project, and work on the sides was able to proceed in parallel. Assume therefore that the sides have a finish-to-finish relationship instead of a finish-to-start relationship, so more than one side can be worked on at the same time. Today is the end of day 3 . Activity Status End of Day 3 Side 1 Complete, spent $1,000 Side 2 Complete, spent $900 Side 360% done, spent $600 Side 470% done, spent $600 Compute the foffowing: 1. PV 2. EV 3. AC 4. BAC 5. CV 6. CPI 7. SV 8. SPI 9. EAC 10. ETC 11. VAC 12. TCPI Comments your results (6 and8)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Pain Management Workbook

Authors: Rachel Zoffness, Mark A. Schumacher

1st Edition

1684036445, 978-1684036448

More Books

Students also viewed these General Management questions