Given the following cost expenditures for a small warehouse project (to include direct and indirect changes): Calculate the peak financial requirement. Sketch a diagram of
Given the following cost expenditures for a small warehouse project (to include direct and indirect changes):
Calculate the peak financial requirement.
Sketch a diagram of the overdraft profile.
What would be the impact on the maximum overdraft of giving the contractor a $25,000 mobilization payment? (Show calculation.)
Assumptions:
The markup for this project is 12%.
Retainage is 10 percent throughout project.
Finance charge is 1.5 percent per month.
Payments are billed at the end of the month and are received one month later.
Month Monthly cost 69,00021,800 17,800 40,900 Directcost+ indirect costStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started