Question

1 Approved Answer

Given the following information, compute the takt time: Total time per shift is 450 minutes per day and there are 2 shifts per day.

Given the following information, compute the takt time: Total time per shift is 450 minutes per day and there

Given the following information, compute the takt time: Total time per shift is 450 minutes per day and there are 2 shifts per day. There are two 15-minute rest breaks and a 45-minute lunch break per shift. Daily demand is 240 units. Net time available per shift: Net time Net time available per day including all shifts: Time available Takt time: (Round your answer to two decimal points.) Takt time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

The given information indicates that for each shift the total time is 450 minutes However within eac... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

What are the differences between transactional and analytic SRM?

Answered: 1 week ago