Golden Winter is a company that operates in the fashion sector, for the needs of the nearest fashion show with the theme Beauty, Casual, Indonesia

Golden Winter is a company that operates in the fashion sector, for the needs of the nearest fashion show with the theme "Beauty, Casual, Indonesia" the company needs to prepare to make several products, namely casual dresses, wedding dresses, kebaya and suits. Processing time as seen in the image below

Start Project Casual Dress 18 Days 2 Tailors Wedding Dress 20 Days 2 Tailors Kebaya 20 Days 2 Tailors Suit 10


a) Draw a resource utilization diagram and calculate the total tailors days needed to run the project!


b) Using the Resource-Limited Scheduling method, assume that only 3 tailors are available. Manage projects with limited resources, include slack values in each completion iteration!
 

Start Project Casual Dress 18 Days 2 Tailors Wedding Dress 20 Days 2 Tailors Kebaya 20 Days 2 Tailors Suit 10 Days 1 Tailors Finish Project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Management Science A Modeling And Cases Studies Approach With Spreadsheets

Authors: Frederick S. Hillier, Mark S. Hillier

5th Edition

978-0077825560, 78024064, 9780077498948, 007782556X, 77498941, 978-0078024061

More Books

Students also viewed these General Management questions

Question

Describe businesss responsibility to the community.

Answered: 1 week ago

Question

=+61. Refer to Exercise 46 of Section 7.4.

Answered: 1 week ago

Question

=+60. Refer to Exercise 42 of Section 7.4.

Answered: 1 week ago