In 2 0 2 4 , the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $ 1

In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
2024: $ 2,640,000
2025: $ 2,300,000
2026: $ 2,926,000
Estimated costs to complete as of year-end
2024: $6,160,000
2025: $2,660,000
2026: $0
Billings during the year
2024: $2,080,000
2025: $2,860,000
2026: $5,060,000
Cash collections during the year
2024: $1,840,000
2025: $2,800,000
2026: $5,360,000
Westgate recognizes revenue over time according to percentage of completion.
2-a. In the journal below, complete the necessary journal entries for the year 2024(credit Cash, Materials, etc. for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025(credit Cash, Materials, etc. for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2026(credit Cash, Materials, etc. for construction costs incurred).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting A Business Perspective

Authors: Roger H. Hermanson, James Don Edwards, Michael W. Maher

7th Edition

0075615851, 978-0075615859

More Books

Students explore these related Accounting questions