In project management, which type of task relationship is represented by Finish-to-Start (FS), where the successor task cannot start until the predecessor task is completed?
In project management, which type of task relationship is represented by "Finish-to-Start" (FS), where the successor task cannot start until the predecessor task is completed? Select one: Constraint Integration Dependency Precedence Clear my choice