IT PROJECT MANAGMENT ASAAAP Calculate the number of people required by using the COCOMO model, if for a given project LOC is 50000. If the

IT PROJECT MANAGMENT
ASAAAP
image

Calculate the number of people required by using the COCOMO model, if for a given project LOC is 50000. If the project team is new to the technologies and project is very difficult for the team Organic Person Months-2.4. KDS11.05 Semi-Detached Person Months-3.0-KDSI1.12 Embedded Person Months-3.6 KDS11.20 Organic Duration-2.5 Effort 0.38 Semi-Detached Duration-2.5 Effort 0.35 Embedded Duration-2.5 Effort 0.32

Step by Step Solution

3.49 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

Ans Expert group is operating so version is Embedded Person Mo... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistics For Business Decision Making And Analysis

Authors: Robert Stine, Dean Foster

2nd Edition

978-0321836519, 321836510, 978-0321890269

More Books

Students also viewed these Electrical Engineering questions