Question:
Jackson Company's overhead rate was based on estimates of $180,000 for overhead costs and 18,000 direct labour hours. Jackson's standards allow 2 hours of direct labour per unit produced. Production in May was 830 units, and actual overhead incurred in May was $19,000. The overhead budgeted for 1,660 standard direct labour hours is $16,120 ($4,500 fixed and $11,620 variable).
(a)Calculate the total, budget, and volume variances for overhead.