Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

M6-1 Assignment Create the following schedule using Microsoft Project (Set the start date as January 6, 2020) Activity Expected Predecessors Duration A 2 days -

image text in transcribed
M6-1 Assignment Create the following schedule using Microsoft Project (Set the start date as January 6, 2020) Activity Expected Predecessors Duration A 2 days - B 3 days A 4 days A D 4 days B, C E 5 days B F 5 days D G 4 days C, E, F and then answer the following questions: 1. Show the critical path (Task/Format/Check Critical Path box). Set current data as baseline schedule (Select Project/Set Baseline and accept defaults). Show comparison to baseline (Click Project/Format/Baseline and check Baseline box). What is the critical path, its duration, and expected finish date? Include a copy of the Gannt Chart 2. Assume that activities B and Care linked with a "finish to finish" relationship. Does that change the expected completion date for the project? How did the schedule change? 3. For activity F, add a lag of three days to its predecessor relationship with activity D. By adding the 3- day lag to F, what is the new expected duration for the project? How did the schedule change? 4. Suppose you now added a start to start relationship between activities F and G to the new Gantt chart. How does this additional relationship change the duration, expected completion date schedule? 5. Submit your project file and a copy of the final Gannet Chart

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions

Question

=+Does this fact violate the efficient markets hypothesis?

Answered: 1 week ago

Question

LO12.3 Explain how demand is seen by a pure monopoly.

Answered: 1 week ago