Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when
Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.0 days Process time 3.2 days Move time 0.5 days Queue time 3.8 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal