Question
Manning, Inc. manufactures a product that has the following standard costs: Direct materials: 40 yards at $2.70 per yard $108 Direct labor: 8 hours at
Manning, Inc. manufactures a product that has the following standard costs:
Direct materials: 40 yards at $2.70 per yard $108
Direct labor: 8 hours at $18.00 per hour 144
Total $252
The following information pertains to July: Direct material purchased: 36,000 yards at $100,440 Direct material used: 36,000 yards Direct labor: 7,500 hours at $139,500 Actual completed production: 1,025 units.
Required: Calculate the direct-material price and quantity variances, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started