Question
Metal Works Corporation has a significant level of manufacturing overhead. After preparing their budget for the next year, management expects the following overhead costs (the
Metal Works Corporation has a significant level of manufacturing overhead. After preparing their budget for the next year, management expects the following overhead costs (the cost driver for each overhead cost pool is also shown):
Activity | Total Cost | Cost Driver |
Maintenance | $25,000 | Machine hours |
Materials receiving | 60,000 | Shipments received |
Machine setups | 10,000 | # of setups |
Inspection | 24,000 | # of inspections |
The expected activity for the year for various cost drivers is:
Direct Labor Hours | 40,000 |
Machine-hours | 12,500 |
Shipments Received | 5,000 |
Setups | 100 |
Quality inspections | 8,000 |
The company is considering accepting a significant production contract. Estimates for the contract are as follows:
Direct materials | $120,000 |
Direct labor (800 hours) | $160,000 |
Number of material shipments received | 250 |
Number of inspections | 400 |
Number of setups | 10 |
Number of machine-hours | 1,500 |
NOTE: Round all per-unit costs to nearest cent.
How much overhead should be allocated to the contract based on Activity-Based Costing?
Group of answer choices
A. $4,800
B. $8,200
C. $2,380
D. $5,300
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started