Question
1 Approved Answer
20) Task ABUAEF D GHID J For the following tasks Duration 5 7 2 +650 12 4 3 6 4 5 Predecessor ABCDE C
20) Task ABUAEF D GHID J For the following tasks Duration 5 7 2 +650 12 4 3 6 4 5 Predecessor ABCDE C G F.H H Successor BU C D.G EEH E F I H I H J Constraints B overlaps A by 3 days. 3 days take place between G ending and H beginning a) Draw the Network Chart - include task id, duration, ES, EF, LS, LF, slack b) What is the critical path? What is slack time for tasks F and G? c) Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 2? Why or Why not? d) Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 5? Why or why not? e) What is slack time and lag time? f) Can the critical path of a project change? Why or why not?
Step by Step Solution
★★★★★
3.32 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
Answer To solve this problem lets go step by step a Draw the Network Chart Task Duration Predecessor Successor Constraints ES EF LS LF Slack A 5 B 0 5 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started