Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected

On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2021 2022 2023
Costs incurred during the year $ 40 $ 80 $ 50
Estimated costs to complete as of December 31 120 60

Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $80 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion.

image text in transcribed

image text in transcribed

image text in transcribed

Percentages of completion Choose numerator | Choose denominator = % complete to date 2021 2022 2023 2021 Recognized in prior years To date Recognized in 2021 Construction revenue Construction expense Gross profit (loss) 0 0 0 $ $ $ $ 2022 Recognized in prior years To date Recognized in 2022 Construction revenue Construction expense Gross profit (loss) $ 2023 Recognized in prior years To date Recognized in 2023 Construction revenue Construction expense Gross profit (loss) $ Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Year Revenue recognized million million Gross Profit (Loss) recognized million 2021 2022 million 2023 million million Required 1 Required 2 Required 3 Suppose the estimated costs to complete at the end of 2022 are $80 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 using the percentage of completion method. (Enter your answers in millions. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date 2022 2022 Recognized in prior Years To date Recognized in 2022 $ Construction revenue Construction expense Gross profit (loss) $ Percentages of completion Choose numerator | Choose denominator = % complete to date 2021 2022 2023 2021 Recognized in prior years To date Recognized in 2021 Construction revenue Construction expense Gross profit (loss) 0 0 0 $ $ $ $ 2022 Recognized in prior years To date Recognized in 2022 Construction revenue Construction expense Gross profit (loss) $ 2023 Recognized in prior years To date Recognized in 2023 Construction revenue Construction expense Gross profit (loss) $ Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Year Revenue recognized million million Gross Profit (Loss) recognized million 2021 2022 million 2023 million million Required 1 Required 2 Required 3 Suppose the estimated costs to complete at the end of 2022 are $80 million instead of $60 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 using the percentage of completion method. (Enter your answers in millions. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date 2022 2022 Recognized in prior Years To date Recognized in 2022 $ Construction revenue Construction expense Gross profit (loss) $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Energy Audit And Survey Of Street Light System A Preliminary Report

Authors: Dr. Manoj Dhondiram Patil

1st Edition

B08GBCWWFY, 979-8676818388

More Books

Students also viewed these Accounting questions

Question

Persuading Your Audience Strategies for

Answered: 1 week ago