PA 1 9 - 4 ( Static ) Consider the AON graph of a project shown above... Consider the AON graph of a project shown

PA 19-4(Static) Consider the AON graph of a project shown above...
Consider the AON graph of a project shown below.
Figure 19.19
A1 to A2. A2 splits to A3 and A5. The path from A3 is A3, A4 A8 and A3, A6, A7, A8. The path from A5 is A5, A7, A8.
The activity times are 3,4,2,5,7,2,2, and 3 days for activities A1
through A8
, respectively. What is the critical path?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Jay Heizer, Barry Render

10th edition

978-0136119418, 136119417, 978-0132163927

More Books

Students also viewed these General Management questions