Question
Perry Products Inc. which makes school desks, uses a standard cost system and provides the following data concerning its operations during the last month (October):
Perry Products Inc. which makes school desks, uses a standard cost system and provides the following data concerning its operations during the last month (October):
Description
Units or $
Units of output
750 units
Standard quantity of materials per desk
16 sq. m.
Standard price per sq. m. materials
$20.00/sq. m.
Actual purchase cost of materials
$259,120
Actual quantity of materials purchased
12,640 sq. m.
Actual quantity of materials used in production.
11,850 sq. m.
Std. hrs allowed per unit for labour
3 hrs. per desk
Std. wage rate
$30.00
Actual wage rate
$31.00
Actual direct labour hours used
2,325 hrs.
Required:
- Prepare fully labeled variance diagrams for Direct Materials and Direct Labour including the specific dollar amounts for all variances.
Prepare journal entries only for materials and labour.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started