Question
Please answer Questions 1, Question 2, Question 3, Question 4, and Question 5. I have each Question in bold so you will be easily able
Please answer Questions 1, Question 2, Question 3, Question 4, and Question 5. I have each Question in bold so you will be easily able to tell each question. When you answer the 5 questions please show detailed steps along with caluclations so I can see how you came up with the answer. Again, please answer ALL 5 QUESTIONS, showing CALCULATIONS and detailed STEPS, as well as the ANSWERS.
Question 1: Use the following for the next five questions:
The following data is given for the Walker Company:
Budgeted production...............................................1,000 units Actual production........................................................980 units
Materials:
Standard price per lb..................................................... ..$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.............11,800 Actual price paid for materials........................................$23,000
Labor:
Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928
The direct material price variance is:
A) $600 F
B) $600 U
C) $80 F
D) $80 U
Question 2: Use the following for the next five questions:
The following data is given for the Walker Company:
Budgeted production...............................................1,000 units Actual production........................................................980 units
Materials:
Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000
Labor:
Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928
The direct material quantity variance is:
A) $600 F
B) $600 U
C) $80 F
D) $80 U
Question 3: Use the following for the next five questions:
The following data is given for the Walker Company:
Budgeted production...............................................1,000 units Actual production........................................................980 units
Materials:
Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000
Labor:
Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928
The direct labor rate variance is:
A) $912 U
B) $912 F
C) $2,100 U
D) $2,100 F
Question 4: Use the following for the next five questions:
The following data is given for the Walker Company:
Budgeted production...............................................1,000 units Actual production........................................................980 units
Materials:
Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000
Labor:
Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928
The direct labor effeciency variance is:
A) $912 F
B) $912 U
C) $2,100 U
D) $2,100 F
Question 5: Use the following for the next five questions:
The following data is given for the Walker Company:
Budgeted production...............................................1,000 units Actual production........................................................980 units
Materials:
Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000
Labor:
Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928
The total direct labor variance is:
$1,188 F
$3,012 U
$1,188 U
Cannot total
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started