Question
PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in
PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in weeks), predecessors, and costs included:
Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A86$1,350$1,950-B98$1,400$2,490-C97$1,000$2,750BD53$2,300$2,700AE43$690$1,150BF32$590$1,300EG106$520$1,000C, D, F
What is the critical path of the project?
B-C-G B-E-F-G A-D-G
If you wanted to shorten the overall duration of the project, which activity would you crash first?
C E B G
What would be the weekly crashing cost of the activity you selected in the previous question? (Display your answer to two decimal places.)
Crash the project by 5 weeks. What is the total cost of crashing the project (just the additional cost, not total project cost)? (Display your answer to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started