Question

1 Approved Answer

PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in

PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in weeks), predecessors, and costs included:

Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A86$1,350$1,950-B98$1,400$2,490-C97$1,000$2,750BD53$2,300$2,700AE43$690$1,150BF32$590$1,300EG106$520$1,000C, D, F

What is the critical path of the project?

B-C-G B-E-F-G A-D-G

If you wanted to shorten the overall duration of the project, which activity would you crash first?

C E B G

What would be the weekly crashing cost of the activity you selected in the previous question? (Display your answer to two decimal places.)

Crash the project by 5 weeks. What is the total cost of crashing the project (just the additional cost, not total project cost)? (Display your answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Scheduling In Industry 4.0 And Cloud Manufacturing

Authors: Boris Sokolov, Dmitry Ivanov, Alexandre Dolgui

1st Edition

3030431762, 9783030431761

More Books

Students also viewed these General Management questions