Question: Preliminary work has been done on a process to recover a valuable chemical from a packed column. The major items of equipment are listed

 Preliminary work has been done on a process to recover a valuable 

Preliminary work has been done on a process to recover a valuable chemical from a packed column. The major items of equipment are listed below. 1). Absorption column: diameter 1 'm, vessel height 30 m, packed height 26 m, packing 50 mm ceramic saddles, vessel carbon steel, operating pressure 5 atm. 2). Condenser: fixed tube sheets, area 30 m, carbon steel shell and Brass tubes, operating pressure 1 atm. 1 atm. 3). Two centrifugal pumps; 10 kW power, Cast steel, delivery pressure 60 barg. 4). Reboiler: fixed tube sheets, area 20 m, SS shell and SS tubes, operating pressure 5). Solvent and product storage tanks: fixed roof, capacity 60 m, carbon steel. Data: pressure factor for pumps = 2.5, 1 .= 1.3 $. Estimate capital investment for this project (Grass Roots): date 2020. Factors: 289 (1979), 400 (2001), 540 (2020).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To estimate the capital investment Grass Roots for this project in 2020 we can use the cost index method This involves adjusting the base cost of the ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!