Problem 4 On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31, 200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow: Contract Costs Est'd Costs Billings incurred to Complete 2022 10, 500, 000 5, 460, 000 20, 540, 000 2023 12, 500, 000 9, 984, 000 13, 156, 000 2024 14, 440, 000 15, 756, 000 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks What is the gross profit for 2024? A. 1, 164, 000 C. 1,724,000 B. 1, 466, 400 D. 1,824,000Problem 5 MOC Construction Company started work on three job sites during the current year . Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below: Site Contract Cost Estimated Costs Billings on Collections Price Incurred to Complete Contract on Billings 5, 000, 000 3, 750,000 5, 000, 000 5,000,000 WN H 7, 000,000 1, 000, 000 4,000,000 900, 000 900, 000 2, 500,000 1, 000, 000 1, 000, 000 1, 500, 000 1, 000, 000 If the company records revenue over time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 31? A. 5, 500,000 C. 250, 000 B. 500,000 D. 100, 000 If the company records revenue at a point in time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 31? A. 5,100,000 C. 250, 000 B. 500, 000 D. 100, 000Problem 9 On January 1, 2017, Build Company entered into a construction contract with an owner to build an oil refinery. The contract has the following characteristics; the oil refinery is highly customized to the owner's specifications and changes to these specifications by the owner are expected over the contract term. The oil refinery does not have an alternative use to the contractor. Non-refundable, interim progress payments are required as a mechanism to finance the contract. The owner can cancel the contract at any time (with a termination penalty) ; any work in process is the property of the owner. As a result, another entity would not need to re-perform the tasks performed to date. Physical possession and title do not pass until completion of the contract. The contractor determines that the contract has a single performance obligation to build the refinery. The majority of evidences suggests that the contractor's performance creates an assets that the customer controls and control is being transferred over time. Build concludes that input method (cost to cost method) instead of output method is a more reasonable method for measuring the progress toward satisfying its performance obligation. 191 1 The contract duration is 3 years with total estimated contract revenue of P300M. The total estimated contract cost as of December 31, 2017 is P200M. The cost incurred during year 2017 as 120M including P20M related to contractor-caused inefficiencies which do not represent/depict the transfer of goods or services to the customer. As of December 31, 2018, the total estimated contract cost becomes 250M due to increase in cost of raw materials. The cost incurred during 2018 is P105M including P5M related to contractor-caused inefficiencies which do not represent/depict the transfer of goods or services to the customer. Under IFRS 15, what is the net income/(loss) to be reported by the company for the years ended December 31, 2017 and 2018