Question

1 Approved Answer

Q 3 . ( 5 MKS ) : Assume we're halfway through a year - long project that has a total budget of $ 1

Q3.(5 MKS): Assume we're halfway through a year-long project that has a total
budget of $100,000. The amount budgeted through this six-month mark is
$55,000. The actual cost through this six-month mark is $45,000.Al
calculation must be shown in the solution.
Calculate the Actual Cost (AC), planned Value(PV),.amed Value
(EV).
Calculate the Schedule Performance Index (SPI) und SPI % Determine
if the project is behind or ahead schedule.
Calculate the Cost Performance Index (CPI) an 1 CPI %.1 etermine if the
Project is over budgeted or under budgeted.
Determine the outcome of the project in terms of cost and schedule.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Basics Computer EngineeringInformation Warehouse Basics From Science

Authors: Odiljon Jakbarov ,Anvarkhan Majidov

1st Edition

620675183X, 978-6206751830

More Books

Students also viewed these Databases questions