Question

1 Approved Answer

Question 1 0 ( 1 point ) The expected activity time in PERT analysis is calculated as the sum of the activity variances, divided by

Question 10(1 point)
The expected activity time in PERT analysis is calculated as
the sum of the activity variances, divided by six.
the simple average of the optimistic, pessimistic, and most likely times. the weighted average of a,m, and b, with m weighted 4 times as heavily as a and b.
the sum of the optimistic, pessimistic, and most likely times.
the sum of the optimistic, pessimistic, and most likely times, divided by six.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Achieving Competitive Advantage

Authors: Jeffrey K. Pinto

4th edition

133798070, 978-0133798074

More Books

Students also viewed these General Management questions

Question

What is descriptive research?

Answered: 1 week ago